Quest Newcastle West Apartment Hotel Newcastle NSW

Quest Newcastle West Apartment Hotel, Newcastle, NSW

Quest Newcastle West Apartment Hotel Newcastle NSW
Quest Newcastle West Apartment Hotel Newcastle NSW

Due to previous, inadequately designed remedial waterproofing solutions, the Quest Newcastle West Apartment Hotel was experiencing large amounts of water ingress to the majority of ground floor hotel rooms, causing significant internal damage and impacting the hotel’s serviceability and capacity levels.

Timeline

Stage 1: Investigation and Specification – 4 weeks

Stage 2: Construction – 5 weeks

Delivering long-term solutions that our clients deserve

Having conducted an in-depth analysis of the site, it was clear that future-proofing the hotel against recurring water ingress issues would require the design of a complex, innovative solution – one that integrated seamlessly with the existing building and its services, and eliminated any structural interference.

With previous remedial works not being carried out to standard, CORE prioritised the development and communication of detailed specification drawings prior to the commencement of any works. This enabled the Client to gain a solid understanding of the issue at hand and provided a visual representation of the proposed solution.

Moving into the construction phase, CORE’s solution entailed a new chemically injected damp-proof course (critically, installed below floor level to prevent rising damp) and saw the application of waterproofing membrane to 80 lineal metres of underground facade externals as well as the installation of a drainage system.

CORE placed great emphasis on maintaining strong communication, managinga robust schedule of weekly meetings and inspections with the Client and contractors throughout the process.

With hotel staff and guests on site, CORE worked closely with key stakeholders to minimise disturbance and ensure the business could continue to operate with no impact on customer experience.

CORE is proud to have delivered the project earlier than the projected completion date and to have provided the Quest Newcastle Hotel with confidence and peace of mind.

Sydney Childrens Hospital Randwick NSW

Sydney Children’s Hospital, Randwick, NSW

Sydney Childrens Hospital Randwick NSW
Sydney Childrens Hospital Randwick NSW

Having successfully completed similar works at Westmead Hospital, CORE was engaged by Mostyn Copper to provide expert advice regarding failed waterproofing roof membrane at the Sydney Children’s Hospital.

Timeline

Stage 1: completed January 2020

Stage 2: currently in progress

Program expected to continue into 2024.

A People-First approach to engineering

Experiencing significant water ingress issues resulting in damages to valuable
equipment and impacting the Hospital’s patient capacity, CORE worked diligently to
deliver a long-term, 2000m2 technical waterproofing solution for our client.

Given the nature of the building and its occupants, along with the impact and
restrictions presented by COVID-19, CORE applied a ‘high priority’ Program of
Works that saw all technical inspections and onsite testing conducted in a safe,
timely and efficient manner.

Stage 1 of remedial works required CORE to strategically determine ideal project
phasing so that affected areas could return to full operational capacity promptly
and prevented further water ingress issues impacting the site.

CORE recommended and designed a 360º cost-effective and sustainable
solution using a premium, innovative waterproofing membrane that could be
installed over existing materials – resulting in a significant decrease to project
time and costs, while minimising wastage. 

With key stakeholders and the impact on end-users front of mind, CORE
placed a strong focus on exceptional communication throughout the project,
ensuring all parties were well informed throughout the process.

Stage 2 of the project is currently underway with works expected to reach
completion in 2024.

iAccelerate University of Wollongong NSW

iAccelerate, University of Wollongong, NSW

iAccelerate University of Wollongong NSW
iAccelerate University of Wollongong NSW

CORE was engaged by Project Coordination to create the facade design for a new, 4,000sqm landmark iAccelerate building located at the University of Wollongong’s Innovation Campus – a centre of Australian innovation and research excellence.

Featuring a ‘plug and go’ expandable space for more than 280 entrepreneurs of fast growth start-up companies, the $14.7m project required meticulous design consideration and innovation in order to meet architectural intent, achieve structural adequacy and deliver an inspiring, functional building for end users.

Timeline

12 months – design

Design and functionality unite

CORE’s attention to detail and unwavering commitment to overcoming a variety of technical challenges saw our team design an efficient and cost-effective facade that not only aligns with the highest standards of Australian design and best practice but also aesthetically brings to life the history of the Illawarra region.

The large, three-storey complex facade necessitated the use of exposed steel columns to meet code requirements for strength and strict serviceability requirements for glazing support. Slender steel box sections were installed in lieu of glazing transoms to transfer wind and gravity loads to the columns. Proprietary aluminium glazing adaptors were specified to support the glazing panels and to seal the building envelope from the external harsh marine environment.

CORE designed a multitude of individual facade structural elements to minimise the quantity of steel on the project which ultimately resulted in:

  • reduced material and transportation costs
  • reduced embodied energy within the facade envelope
  • smaller structural materials which in turn reduced the risk to site operators

All connections were carefully considered and detailed by CORE to ensure the facade would be buildable without compromising its integrity. Moisture naturally forming within the facade was designed to escape the envelope
via carefully positioned glazing spigots and weepholes between capping elements. These weepholes also allow for thermal variations between the clip on covers and supporting steel.

Notably, the project was awarded Winner of the 2017 NSW MBA South-East Region Excellence in Building Awards – Commercial Building category and Winner of the 2016 NSW MBA Excellence in Building Awards – Tertiary Building $10 – $25m category.

 

361 Military Rd Mosman A 361 Military Road Mosman NSW

361 Military Road, Mosman, NSW

361 Military Rd Mosman A 361 Military Road Mosman NSW
361 Military Rd Mosman B 361 Military Road Mosman NSW

Faced with excessive stormwater issues causing internal leaks throughout several apartments, Executive Strata needed the support of a trusted partner to conduct a thorough assessment of the site. Signs of significant water ingress with the building’s passenger lift shaft was of additional concern.
Previous assessments by other parties had indicated a new roof and downpipes would need to be installed on top of existing structure as the existing drainage system was not visible from the building’s exterior.

The Challenge: finding the best solution

Executive Strata engaged CORE to investigate the building’s stormwater and water leakage issues and advise on remedial action.
Going beyond the brief, CORE conducted a thorough whole-of-site inspection to assess and identify other potential areas of concern and impact over and above the affected areas.

CORE’s due diligence proves critical

In addition to the lift shaft, the CORE team uncovered previously undetected water ingress within the building’s car lift and oil room where electrical and hydraulic cabling was at immediate risk of short-circuiting, deterioration and posing a danger to residents.
CORE then sought to obtain the plans of the existing drainage system installed by stormwater/hydraulic consultants. This due diligence was of paramount importance as it revealed that Executive Strata could repair, rather than replace, the existing system saving them a significant amount of time and money.

The Outcome: CORE’s holistic approach mitigates risk and delivers savings

CORE’s rigorous approach to this project located the root cause of each issue and enabled the team to deliver a comprehensive assessment report, providing Executive Strata with a complete view of the issues at hand.
Importantly, a long-term solution could now be undertaken, providing the assurance of reduced risk on future issues while saving money, time and impact on residents’ safety.

Griffith Base Hospital Redevelopment NSW

Griffith Base Hospital Redevelopment, NSW

Griffith Base Hospital Redevelopment NSW
Griffith Base Hospital Redevelopment NSW

CORE was engaged by Project Coordination to support the delivery of NSW Health Infrastructure’s $10+ million upgrade to Griffith Hospital, NSW.

The project involved the construction of a new Ambulatory Care Hub as well as extensions to the hospital’s Critical Care and Inpatient Units to increase patient capacity, enhance service functionality and welcome the addition of new support areas.
The plan also required improvements to existing car park facilities along with other external works.

Timeline

6 months – design
12 months – construction

Our Approach: achieving a detailed understanding of the client’s needs

When working within the Health sector, dedicating the necessary time to listen and develop a strong understanding of a client’s needs is more critical than ever.

From the initial consultation stage, the CORE team ensured that the right amount of time was spent upfront in order to deliver a better long-term result.

As always, strong, open lines of communication played a key role in determining project success and saw CORE working alongside on-site teams as well as the hospital board to ensure proposed solutions aligned with the hospital’s operational requirements.

The Outcome: delivering optimal design, reducing time and costs

The redevelopment of Griffith Base Hospital was a multi-layered, complex project with a clear objective to significantly enhance the hospital precinct, its processes and operations.

CORE’s detailed and thorough approach to the project’s design phase was invaluable.

Our 3D modelling capabilities enabled key stakeholders to seamlessly visualise the proposed solutions and facilitated critical conversations during the early stages of the project – saving significant amounts of time and money during the construction phase.

The 12-month construction stage was delivered to scope, on time and to budget with the hospital remaining fully operational throughout the period.

Cooma Hospital Redevelopment NSW

Cooma Hospital Redevelopment, NSW

Cooma Hospital Redevelopment NSW
Cooma Hospital Redevelopment NSW

NSW Health Infrastructure were redeveloping the Cooma Hospital to deliver enhanced services, facilities and care to Cooma and surrounding communities.

With an investment of over $24 million, the project involved a staged extension and refurbishment of two adjacent blocks at the hospital campus. The upgrades saw the development of a new Maternity Ward as well as an expanded and improved Emergency Department and relocation of Ambulatory Care, Pathology and Medical Imaging.

The CORE advantage: collaborative and integrated solutions

Having strong experience in the Aged Care/Health sector, and in delivering solutions for complex, live environments, CORE was engaged to deliver a multi-disciplinary project solution that included the following services:

  • Structural
  • Civil
  • Mechanical
  • Electrical
  • Fire
  • Hydraulics

Working closely with Project Coordination over a 2-year design and construction period, CORE delivered flexible, cost-effective engineering for Cooma Hospital that required seamless communication and integration across all stakeholders and services – ensuring the best possible solutions and outcomes were achieved along the way.

Critically, the rollout of our strategies and services enabled Cooma Hospital to remain fully operational throughout the project period.

9 Hunter St A 361 Military Road Mosman NSW

9 Hunter St, Sydney, NSW

9 Hunter St Sydney NSW
9 Hunter St Sydney NSW

Located in the heart of the Sydney CBD, 9 Hunter St is a 17 level office tower with a multi-tenant profile situated above one of the city’s busiest food courts.

CORE was engaged in 2019 as part of plans to undertake a major refurbishment of the lobby area that would include upgrades and alterations to the commercial entry to the existing building, inclusion of a new accessible ramp, fire safety upgrades, shopfront and awning along with bespoke finishes to the foyer and lift lobby interiors such as the undulating ceiling, double-height glass façade and portal lighting.

The objective of the works was to enhance the environment and areas available for lease with cutting edge design, transforming the ground level of one of Sydney’s best situated office towers.

Timeline

6 months – design
12 months – construction

CORE – a partner of choice

As a multi-disciplinary consultancy, continuously adding value throughout the building’s lifecycle, CORE were well equipped to deliver an end-to-end project solution.

Over an 18-month period, our team in conjunction with our project partners delivered all major structural and building services works achieving significant aesthetic, functional, accessibility and safety improvements for tenants and staff alike.

Setting the building apart, one of the most impressive design features is the change from a single-height to a double-height facade which required the complete relocation of major services. Complemented by architecturally designed, undulating dowel with dowel and entry portal lighting designed by CORE, the lobby is the perfect example of design and functionality aligned.

Shoalhaven Hospital Multi-Deck Carpark NSW

Shoalhaven Hospital Multi-Deck Carpark, NSW

Shoalhaven Hospital Multi-Deck Carpark NSW
Shoalhaven Hospital Multi-Deck Carpark NSW

In a major milestone for communities of Shoalhaven and surrounds, Health Infrastructure recognised the need for additional car parking spaces to accommodate the growing use of Shoalhaven Hospital -improving connectivity and allowing easier and more convenient access for patients and visitors.

Timeline

12 months – design
12 months – construction

The Challenge: finding the best solution

Project Coordination engaged CORE for the demolition and development of the new multi-deck car park and security room.
The design stage was critical to ensuring the new car park capacity was optimised and would visually integrate and align with the hospital’s masterplan. Complex, existing issues on site needed to be overcome which saw CORE working closely with builders and clients to alleviate concerns safely and with timely and cost efficient solutions.

CORE’s key areas of focus were: capacity requirements, coordination with the existing helipad and impacts on helicopter approach to hospital, aesthetics, water diversion/flow path management, lighting and hydraulics.

The project was constructed within the challenging environment of an operating hospital and adjacent to a cancer care unit. Close collaboration and communication with stakeholders was required to ensure minimal interruption to clinical services and hospital access; as well as a focus on infection control due to the close proximity of immunocompromised patients.

The Outcome: car park capacity increased by over 50%

Construction on the NSW Government’s $11.8 million multi-storey car park was completed in June 2020.

The new five split-level car park provides patients and visitors with more than 300 new spaces, increasing the hospital’s overall parking capacity to over 550 spaces and features a stunning facade inspired by the colours and landscape art of Shoalhaven luminary Arthur Boyd.

Notably, the project was awarded Winner of the NSW MBA Building in Excellence Awards in the ‘Best Public Building $10-15M’ category.